Sites Reservoir gets its final water permit, and the Tri-Valley's Zone 7 may buy in
The Good Day Oakland team
California's largest water-storage project in 50 years got its final water permit this month. On Nov. 4, the State Water Resources Control Board voted unanimously to approve the permit for Sites Reservoir, which would hold up to 1.5 million acre-feet in Colusa County.
Sites' price estimate has climbed from $3.9 billion to $7.5 billion
Source: The Independent
View as table
| Value | |
|---|---|
| Initial planning | $3.9 billion |
| 2025 estimate | $6.8 billion |
| California Water Commission | $7.5 billion |
- Diversion limit: up to 986,000 acre-feet a year
- Diversion season: November to mid-June, after senior water rights
- Zone 7 stake considered: 30,000 to 60,000 acre-feet
- Zone 7 treated water rates: up 4.5% a year over four years
Zone 7 Water Agency, which wholesales water in the Tri-Valley, expects to make its final decision in early 2027. Roughly $24.7 million of ratepayer revenue will go toward the reservoir through fiscal year 2036, assuming a 30,000-acre-foot share. Environmental groups and tribal members oppose the project over Sacramento River diversions and sacred sites.
Zone 7 could decide on Sites in early 2027
- Oct. 2026Zone 7 board votes unanimously to raise treated water rates 4.5% annually.
- Nov. 4State Water Board votes unanimously to approve the Sites permit.
- Early 2027Zone 7 expects to make its final decision on participating.
- Summer '27Construction of the reservoir could begin as early as then.
Source: The Independent