East BayFriday, November 20
Berkeley's City Council unanimously approved a pier and electric ferry to San Francisco
The Good Day Oakland team
Berkeley's pier has been closed for more than a decade, and ferry service is a step closer. On Tue., Nov. 17, the City Council voted unanimously to certify the environmental report and approve the Pier-Ferry project and its use permit. The route is expected to carry more than 1,000 riders each weekday. The vote doesn't commit any construction money, so the ferry still depends on grants.
Berkeley's pier went from ferry landing to closed to approved
- 1926The Golden Gate Ferry Company builds the Berkeley Municipal Pier.
- 1937Ferry service ends, less than a year after the Bay Bridge opens.
- July 2015The pier closes to the public because of structural problems.
- Nov. 3Berkeley publishes the final environmental impact report.
- Nov. 17The Berkeley City Council votes unanimously to approve the project.
- Spring '28Officials aim to begin the first construction phase, pending funding.
Sources: San Francisco News, San Francisco Patch
- Pier: 1,080 feet, plus a 400-foot breakwater
- Construction phase: estimated at $139 million, excluding dredging, vessels and solar panels
- Service: weekday commute hours, plus all day on weekends
SF Bay Ferry's board allocated $1.3 million on Thursday, Nov. 12, for the plans, and designers have completed 60% of the design.
Designers have finished 60% of the pier ferry project's design
60%Share of the project's design completed
Source: San Francisco Patch
View as table
| Value | |
|---|---|
| Share of the project's design completed | 60% |
| Expected by end of 2026 | 90% |
Not everyone's on board. Critics note Berkeley designated the site a Marine Park in 1965 and that Measure L requires a public vote before a park is developed. The Save the Berkeley Pier campaign estimates the project will cost roughly $170 million.
Sources: San Francisco News, San Francisco Patch